Kurmuk Gold Mine Moves Toward First Gold Pour as Commissioning Advances

By Muluken Yewondwossen

Kurmuk Gold Mine Plc (KGM), the Ethiopian subsidiary of Canada-based Allied Gold Corporation, has formally notified the Ministry of Mines that it is advancing toward its first gold pour as the company moves into the final stages of commissioning and production testing at its flagship Kurmuk project in western Ethiopia.

In a notification letter signed by Brox Worku, General Manager of Kurmuk Gold Mine Plc, and obtained by EtBusinessView, the company said the mine has reached an advanced stage of construction completion, commissioning and operational readiness.

“KGM expects to undertake its first gold pour during the forthcoming hot commissioning and production testing period.”

Located approximately 700 kilometres west of Addis Ababa in the Benishangul-Gumuz Regional State, the Kurmuk operation has recently achieved several critical milestones, including the successful energization of the power line connecting the mine to Ethiopia’s national electricity grid and the commissioning of the crushing circuit, with the first ore already fed into the processing facility.

“Mining activities are progressing as planned, ore stockpiles have been established to support the ramp-up of operations, and commissioning of the remaining processing circuits is continuing,” the company said in its notification to the Ministry.

Against this backdrop, KGM said it expects to undertake its first gold pour during the forthcoming hot commissioning and production testing period.

The company, however, made clear that the initial gold pour should not be interpreted as the start of commercial production.

“For the avoidance of doubt, this notification relates solely to the first gold pour occurring during commissioning and production testing and shall not be construed as notice of the commencement of commercial production,” the company stated.

KGM said formal notification of commercial production would be submitted separately in accordance with Ethiopia’s regulatory requirements and the provisions of its Mining Development Agreement signed on September 30, 2021.

The company also said it is coordinating with the Ministry of Mines and other relevant government authorities on arrangements covering gold verification, security, transportation, sale and export as the project progresses through commissioning and production testing.

The latest development follows the delivery of first ore to the commissioned crushing circuit earlier this month, marking a significant step in the mine’s transition from construction to operational ramp-up. Allied Gold has said it expects ore to be introduced into the grinding circuit in the coming weeks, with first gold expected to follow soon thereafter.

Allied Gold has positioned Kurmuk as one of its key growth assets. Once fully operational, the mine is expected to produce between 240,000 and 270,000 ounces of gold during its first full year of production, rising to approximately 300,000 ounces in the following year.

The company has set an initial strategic mine-life target of 15 years, with average annual production expected to remain at least 240,000 ounces. Over the first four years of operation, Allied expects Kurmuk to average approximately 290,000 ounces annually.

The project is also supported by access to Ethiopia’s national grid, which Allied describes as a significant milestone for the operation and an important factor in its expected cost profile.

Kurmuk currently holds 2.7 million ounces of Proven and Probable Mineral Reserves across the Dish Mountain and Ashashire deposits, which are expected to provide the initial ore feed for the operation.

Beyond the initial mine plan, Allied Gold has identified substantial exploration potential across a 1,450-square-kilometre land package surrounding the project. The company expects further exploration and optimization to have the potential to expand mineral inventories, extend mine life and provide additional flexibility for future production.

For Ethiopia, the approaching first gold pour marks another major milestone in the development of one of the country’s largest emerging gold mining operations. The project’s transition into production is also expected to establish Kurmuk as a significant contributor to Allied Gold’s overall production and cash flows.

KGM said it remains committed to transparency, regulatory compliance and continued cooperation with the Ethiopian government as it completes commissioning and prepares for commercial operations.SECO

Related

Government Shifts Toward Longer-Term Treasury Bills as Investor Demand Grows

By Muluken Yewondwossen, Special to EBV The Ethiopian government is...

Houthi Control of Perim Raises New Maritime Risks for Ethiopia and the Horn of Africa

Ethiopia faces a growing economic and strategic risk as...

CETU Takes EIH Labour Dispute to Justice Minister

The tension between Ethiopian Investment Holdings (EIH) and the...

Tariku Demissie Named Interim Ethio Telecom CEO

ETBusinessView has learned that Tariku Demissie, Ethio Telecom’s Chief...

From Addis Ababa to the U.S. Congress: The Rise of Melat Kiros

In the early hours of July 1, 2026, Melat...

Popular Categories